Data ยท Building safety
Cladding remediation map
Progress on fixing unsafe cladding on residential buildings of 11 metres and over in England, by council, updated each month from the government's own data.
By 31 October 2026, work was finished on 1,883 of the 4,740 buildings with unsafe cladding the government monitors (40%), and underway on 754 more.
What makes the outside wall of a tall block safe? See the external wall and its cavity barriers in 3D
October 2026 release, figures at 31 October 2026, published 25 November 2026
Finished
1,883
40% of 4,740 monitored, including those awaiting sign-off
Underway
754
16% of monitored buildings
Not started
2,103
44% of monitored buildings
All affected buildings
5,900 to 7,400
The government's estimate (March 2026), monitored or not
Each council is shaded by the share of its monitored buildings where work is finished. Councils with fewer than 10 monitored buildings of 11 metres and over with unsafe cladding are left out of the release's council figures, so that no building can be identified; they are grey.
- 0% to under 20% finished
- 20% to under 40% finished
- 40% to under 60% finished
- 60% to under 80% finished
- 80% or more finished
- Fewer than 10 monitored buildings
The regions
| Region | Finished | Share finished | Underway | Not started | Total |
|---|---|---|---|---|---|
| London | 957 | 38% | 398 | 1,135 | 2,490 |
| South East | 243 | 39% | 101 | 276 | 620 |
| North West | 225 | 45% | 79 | 200 | 504 |
| West Midlands | 167 | 61% | 25 | 81 | 273 |
| South West | 74 | 27% | 44 | 154 | 272 |
| East of England | 76 | 28% | 56 | 137 | 269 |
| Yorkshire and The Humber | 79 | 49% | 33 | 49 | 161 |
| East Midlands | 29 | 34% | 14 | 42 | 85 |
| North East | 33 | 50% | 4 | 29 | 66 |
Every council in the release (70)
The release gives each council's buildings as a band, not an exact count, and the share at each stage.
| Council | Buildings monitored | Finished | Underway | Not started |
|---|---|---|---|---|
| Barking and Dagenham | 11-50 | 32% | 30% | 38% |
| Barnet | 51-100 | 53% | 17% | 31% |
| Basingstoke and Deane | 11-50 | 29% | 52% | 19% |
| Bexley | 11-50 | 47% | 26% | 26% |
| Birmingham | 201-400 | 73% | 7% | 20% |
| Bournemouth, Christchurch and Poole | 11-50 | 46% | 7% | 48% |
| Bradford | 11-50 | 33% | 17% | 50% |
| Brent | 51-100 | 38% | 16% | 46% |
| Brighton and Hove | 51-100 | 33% | 20% | 46% |
| Bristol, City of | 101-200 | 24% | 11% | 65% |
| Bromley | 11-50 | 39% | 6% | 56% |
| Cambridge | 11-50 | 16% | 10% | 73% |
| Camden | 51-100 | 41% | 17% | 42% |
| Coventry | 11-50 | 17% | 25% | 58% |
| Croydon | 51-100 | 36% | 11% | 53% |
| Dacorum | 11-50 | 5% | 20% | 75% |
| Dartford | 11-50 | 64% | 9% | 27% |
| Ealing | 51-100 | 58% | 7% | 35% |
| Eastbourne | 11-50 | 56% | 13% | 31% |
| Elmbridge | 11-50 | 38% | 0% | 62% |
| Enfield | 11-50 | 36% | 9% | 55% |
| Gateshead | 11-50 | 42% | 0% | 58% |
| Gosport | 11-50 | 73% | 0% | 27% |
| Greenwich | 101-200 | 41% | 24% | 35% |
| Hackney | 101-200 | 48% | 13% | 39% |
| Hammersmith and Fulham | 11-50 | 27% | 11% | 62% |
| Haringey | 11-50 | 46% | 21% | 33% |
| Harrow | 11-50 | 41% | 9% | 50% |
| Havering | 11-50 | 44% | 8% | 47% |
| Hertsmere | 11-50 | 15% | 55% | 30% |
| Hillingdon | 11-50 | 23% | 26% | 52% |
| Hounslow | 51-100 | 48% | 13% | 40% |
| Ipswich | 11-50 | 34% | 34% | 31% |
| Islington | 101-200 | 21% | 31% | 49% |
| Kensington and Chelsea | 11-50 | 45% | 27% | 27% |
| Lambeth | 51-100 | 38% | 13% | 49% |
| Leeds | 51-100 | 54% | 24% | 22% |
| Leicester | 11-50 | 28% | 20% | 52% |
| Lewisham | 51-100 | 34% | 16% | 51% |
| Liverpool | 51-100 | 35% | 22% | 43% |
| Maidstone | 11-50 | 28% | 32% | 40% |
| Manchester | 201-400 | 48% | 13% | 39% |
| Medway | 11-50 | 44% | 11% | 44% |
| Merton | 11-50 | 24% | 29% | 48% |
| Milton Keynes | 11-50 | 14% | 10% | 76% |
| Newcastle upon Tyne | 11-50 | 50% | 9% | 41% |
| Newham | 101-200 | 42% | 15% | 43% |
| North Somerset | 11-50 | 18% | 18% | 64% |
| Norwich | 11-50 | 63% | 15% | 22% |
| Nottingham | 11-50 | 45% | 11% | 45% |
| Plymouth | 11-50 | 30% | 23% | 47% |
| Portsmouth | 11-50 | 40% | 0% | 60% |
| Reading | 11-50 | 53% | 17% | 30% |
| Redbridge | 11-50 | 27% | 3% | 70% |
| Richmond upon Thames | 11-50 | 64% | 36% | 0% |
| Salford | 51-100 | 49% | 18% | 33% |
| Sheffield | 11-50 | 44% | 14% | 42% |
| Slough | 11-50 | 50% | 5% | 45% |
| Solihull | 11-50 | 0% | 9% | 91% |
| Southampton | 101-200 | 49% | 13% | 38% |
| Southwark | 101-200 | 27% | 11% | 62% |
| Stoke-on-Trent | 11-50 | 0% | 25% | 75% |
| Sunderland | 11-50 | 64% | 9% | 27% |
| Sutton | 11-50 | 42% | 5% | 53% |
| Tower Hamlets | Over 400 | 37% | 19% | 44% |
| Trafford | 11-50 | 37% | 5% | 58% |
| Waltham Forest | 11-50 | 41% | 2% | 57% |
| Wandsworth | 101-200 | 43% | 9% | 49% |
| Westminster | 51-100 | 50% | 3% | 47% |
| Woking | 11-50 | 13% | 20% | 67% |
England's monitored buildings by stage, one bar per monthly release. December 2025 is the first month on the current basis: from then, social housing is counted from landlords' own reports, and the government says earlier months are not directly comparable.
Show the figures as a table
| Month | Finished | Underway | Not started | Total |
|---|---|---|---|---|
| December 2025 | 1,475 | 693 | 1,958 | 4,126 |
| January 2026 | 1,500 | 695 | 1,996 | 4,191 |
| February 2026 | 1,521 | 777 | 2,012 | 4,310 |
| March 2026 | 1,531 | 868 | 1,923 | 4,322 |
| April 2026 | 1,544 | 871 | 1,963 | 4,378 |
| May 2026 | 1,672 | 659 | 2,080 | 4,411 |
| June 2026 | 1,681 | 698 | 2,090 | 4,469 |
| July 2026 | 1,833 | 718 | 2,146 | 4,697 |
| August 2026 | 1,849 | 722 | 2,153 | 4,724 |
| September 2026 | 1,878 | 743 | 2,111 | 4,732 |
| October 2026 | 1,883 | 754 | 2,103 | 4,740 |
By height
| Height | Finished | Share finished | Underway | Not started | Total |
|---|---|---|---|---|---|
| 18 metres and over | 1,286 | 50% | 359 | 952 | 2,597 |
| 11 to 18 metres | 597 | 28% | 395 | 1,151 | 2,143 |
By tenure
| Tenure | Finished | Share finished | Underway | Not started | Total |
|---|---|---|---|---|---|
| Private | 1,012 | 35% | 512 | 1,331 | 2,855 |
| Social housing | 775 | 43% | 238 | 771 | 1,784 |
| Other | 96 | 95% | 4 | 1 | 101 |
Buildings that developers who signed the developer remediation contract must fix, as the government reports them, at 31 July 2026. These figures are quarterly, so they can be older than the rest of the page. Under the Remediation Acceleration Plan, developers aimed to start or finish work on 80% of their buildings by the end of July 2026; the last column gives each one's share for comparison.
| Developer | Need work | Not started | Underway | Finished | Started or finished |
|---|---|---|---|---|---|
| Barratt Redrow PLC | 541 | 392 | 60 | 89 | 28% |
| Bellway PLC | 408 | 168 | 218 | 22 | 59% |
| Crest Nicholson Holdings PLC | 282 | 92 | 179 | 11 | 67% |
| Taylor Wimpey PLC | 250 | 133 | 39 | 78 | 47% |
| Vistry Group PLC | 138 | 68 | 23 | 47 | 51% |
| Telford Homes Limited | 103 | 96 | 7 | 0 | 7% |
| The Berkeley Group Holdings PLC | 87 | 28 | 13 | 46 | 68% |
| Fairview Holdings Limited | 81 | 22 | 42 | 17 | 73% |
| Weston Group PLC | 75 | 2 | 23 | 50 | 97% |
| Persimmon Public Limited Company | 66 | 28 | 29 | 9 | 58% |
| Galliard Group Limited | 50 | 30 | 3 | 17 | 40% |
| Lendlease Europe Holdings Limited | 40 | 14 | 24 | 2 | 65% |
| London Square Development (Holdings) Limited | 39 | 1 | 38 | 0 | 97% |
| Miller Homes Limited | 37 | 3 | 13 | 21 | 92% |
| Ballymore Limited | 34 | 21 | 2 | 11 | 38% |
| McCarthy & Stone Limited | 25 | 6 | 3 | 16 | 76% |
| Morgan Sindall Group PLC (parent company for Lovell and Muse) | 24 | 10 | 2 | 12 | 58% |
| Cala Group (Holdings) Limited | 22 | 8 | 9 | 5 | 64% |
| Hill Holdings Limited | 22 | 10 | 1 | 11 | 55% |
| Sorbon Group Limited (parent company for Shanly Homes) | 20 | 6 | 6 | 8 | 70% |
| Dandara Living Holdings Limited | 19 | 16 | 2 | 1 | 16% |
| Seven Capital PLC | 19 | 17 | 2 | 0 | 11% |
| Rydon Group Holdings Limited | 16 | 1 | 1 | 14 | 94% |
| Bouygues (UK) Limited | 15 | 8 | 0 | 7 | 47% |
| MJ Gleeson PLC | 15 | 9 | 1 | 5 | 40% |
| Wates Group Limited | 14 | 7 | 0 | 7 | 50% |
| Watkin Jones PLC | 13 | 6 | 5 | 2 | 54% |
| Grosvenor Developments Limited | 12 | 4 | 7 | 1 | 67% |
| Tilia Homes Limited | 8 | 2 | 4 | 2 | 75% |
| Frasers Property (UK) Ltd | 7 | 2 | 0 | 5 | 71% |
| Land Securities Group PLC | 7 | 4 | 3 | 0 | 43% |
| Brighton STM Group Holding Company Limited (formally St. Modwen Group Holdings Company Limited) | 6 | 5 | 0 | 1 | 17% |
| Bewley Group Limited | 5 | 0 | 4 | 1 | 100% |
| Jelson Holdings Limited | 5 | 0 | 3 | 2 | 100% |
| The British Land Company PLC | 4 | 2 | 2 | 0 | 50% |
| Morris Homes Group Limited | 3 | 1 | 0 | 2 | 67% |
| Arada London Ltd | 2 | 0 | 0 | 2 | 100% |
| Canary Wharf Group PLC | 2 | 2 | 0 | 0 | 0% |
| Churchill Living (formerly Churchill Retirement PLC) | 2 | 0 | 1 | 1 | 100% |
| Pegasus Homes (formerly Lifestory Group) | 1 | 0 | 0 | 1 | 100% |
| Viva Midco Limited (parent company for Avant Homes) | 0 | 0 | 0 | 0 | n/a |
| Developers with five buildings or fewer, combined | 7 | 3 | 2 | 2 | 57% |
| All developers | 2,526 | 1,227 | 771 | 528 | 51% |
Counted in the combined row: Abbey Developments Limited, Allison Homes Group Limited, Bloor Investments Limited, Broadthorpe Limited (parent company for William Davis Homes), C.G. Fry and Son Limited, Croudace Homes Group Limited, Emerson Developments (Holdings) Limited (parent company for Jones Homes), Hopkins Home Group Limited, Keepmoat Limited, Rowland Group Limited, Story Homes Limited, Strata Homes Group Limited.
Councils can take enforcement action against building owners under the Housing Act 2004. Buildings acted on, hazard ratings and notices served, by council, at 31 October 2026. These tables name a different set of councils from the map.
| Council | Buildings | Category 1 | Category 2 | Notices served | With inspection team |
|---|---|---|---|---|---|
| Westminster | 153 | 6 | 146 | 24 | 3 |
| Hammersmith and Fulham | 107 | 0 | 101 | 12 | 2 |
| Tower Hamlets | 72 | 14 | 44 | 42 | 23 |
| Southwark | 70 | 29 | 36 | 46 | 5 |
| Newham | 59 | 13 | 38 | 60 | 31 |
| Nottingham | 54 | 1 | 52 | 15 | 3 |
| Camden | 46 | 3 | 42 | 23 | 6 |
| Lambeth | 38 | 1 | 37 | 21 | 2 |
| Islington | 24 | 3 | 19 | 23 | 3 |
| Greenwich | 23 | 3 | 8 | 10 | 18 |
| Hackney | 23 | 10 | 8 | 14 | 18 |
| Birmingham | 22 | 2 | 16 | 16 | 18 |
| Newcastle upon Tyne | 19 | 1 | 13 | 7 | 2 |
| Hillingdon | 18 | 4 | 8 | 7 | 1 |
| Bristol, City of | 16 | 0 | 14 | 0 | 0 |
| City of London | 14 | 8 | 4 | 10 | 0 |
| Liverpool | 13 | 3 | 7 | 6 | 11 |
| Barnet | 11 | 6 | 5 | 9 | 4 |
| Bournemouth, Christchurch and Poole | 10 | 6 | 4 | 8 | 3 |
| Redbridge | 10 | 6 | 3 | 8 | 5 |
| Barking and Dagenham | 7 | 2 | 5 | 4 | 3 |
| Croydon | 6 | 2 | 4 | 1 | 6 |
| Milton Keynes | 6 | 0 | 1 | 1 | 0 |
| Plymouth | 6 | 2 | 4 | 6 | 1 |
| Portsmouth | 6 | 1 | 2 | 2 | 4 |
| Ealing | 5 | 2 | 3 | 2 | 5 |
| Reading | 5 | 0 | 5 | 0 | 0 |
| Wandsworth | 4 | 1 | 3 | 1 | 4 |
| Southampton | 3 | 1 | 0 | 1 | 3 |
| Brent | 2 | 1 | 1 | 0 | 2 |
| Dacorum | 2 | 0 | 2 | 2 | 0 |
| Hounslow | 2 | 1 | 1 | 2 | 1 |
| Sunderland | 2 | 1 | 1 | 1 | 1 |
| Waltham Forest | 2 | 0 | 2 | 1 | 2 |
| Bradford | 1 | 0 | 1 | 1 | 0 |
| Manchester | 1 | 0 | 0 | 0 | 1 |
| Medway | 1 | 1 | 0 | 1 | 0 |
| Salford | 1 | 0 | 1 | 0 | 1 |
| Sheffield | 1 | 0 | 0 | 0 | 1 |
| Sutton | 1 | 1 | 0 | 1 | 1 |
| Brighton and Hove | 0 | 0 | 0 | 0 | 0 |
| Bromley | 0 | 0 | 0 | 0 | 0 |
| Calderdale | 0 | 0 | 0 | 0 | 0 |
| Gateshead | 0 | 0 | 0 | 0 | 0 |
| Haringey | 0 | 0 | 0 | 0 | 0 |
| Harrow | 0 | 0 | 0 | 0 | 0 |
| Ipswich | 0 | 0 | 0 | 0 | 0 |
| Kensington and Chelsea | 0 | 0 | 0 | 0 | 0 |
| Kingston upon Thames | 0 | 0 | 0 | 0 | 0 |
| Kirklees | 0 | 0 | 0 | 0 | 0 |
| Leeds | 0 | 0 | 0 | 0 | 0 |
| Leicester | 0 | 0 | 0 | 0 | 0 |
| Lewisham | 0 | 0 | 0 | 0 | 0 |
| Maidstone | 0 | 0 | 0 | 0 | 0 |
| Merton | 0 | 0 | 0 | 0 | 0 |
| North Somerset | 0 | 0 | 0 | 0 | 0 |
| Norwich | 0 | 0 | 0 | 0 | 0 |
| Slough | 0 | 0 | 0 | 0 | 0 |
| Thanet | 0 | 0 | 0 | 0 | 0 |
| Trafford | 0 | 0 | 0 | 0 | 0 |
| Windsor and Maidenhead | 0 | 0 | 0 | 0 | 0 |
| Other councils | 82 | 18 | 45 | 24 | 11 |
| England | 948 | 153 | 686 | 412 | 205 |
Category 1 is the most serious hazard rating. "With inspection team" counts buildings inspected with the Joint Inspection Team, which supports councils on high-rise buildings.
If you live in a block of flats: the map shows how your council area is doing, not your building. Ask your building owner or managing agent whether your building is in a government programme and when work is due. Qualifying leaseholders do not pay for cladding remediation.
If you own or manage buildings: the government expects every building of 11 metres and over with unsafe cladding to be fixed, have a completion date, or face penalties by the end of 2029, and a Bill before Parliament would make remediation a legal duty.
If your firm does this work: 2,103 monitored buildings had not started at 31 October 2026. The regions and councils with most still to start show where the work is.
Is my building on the list?
The government does not publish addresses, so this map cannot show individual buildings. It gives progress figures only for councils with at least 10 monitored buildings of 11 metres and over with unsafe cladding, so that no building can be identified. At 31 October 2026 the government was monitoring 4,740 buildings. To find out about your own building, ask the building owner or managing agent, or your council.
Who pays for cladding remediation?
Under the Building Safety Act 2022, whose leaseholder protections came into force on 28 June 2022, qualifying leaseholders in buildings above 11 metres or five storeys are protected from all cladding remediation costs. What they can be charged for other historical safety defects is capped and spread over 10 years, and some leaseholders pay nothing towards them. Developers who signed the developer remediation contract fix buildings over 11 metres they developed or refurbished in the last 30 years; government schemes fund others.
When does remediation have to be finished?
The government's Remediation Acceleration Plan says that by the end of 2029 every residential building of 18 metres and over in a government funded scheme will be remediated, and every building of 11 metres and over with unsafe cladding will be remediated, have a date for completion, or its landlord will be liable for penalties. The Building Safety (Remediation of Unsafe Cladding etc) Bill, introduced to Parliament on 14 October 2026, would make remediation a legal duty. If it becomes law, buildings must be assessed within 12 months of Royal Assent and a Remediation Compliance Plan produced within 15 months.
Remediation Acceleration Plan update, July 2025, GOV.UKGuide to the Bill, GOV.UK
What is the Cladding Safety Scheme?
The Cladding Safety Scheme is government funding for remediating unsafe cladding on residential buildings of 11 metres and over in England where a responsible developer cannot be identified, traced or held responsible. The application is made by the person or organisation responsible for repairing the building (such as the freeholder, a right-to-manage company or a housing association), not by individual leaseholders. Homes England runs it.
Does this cover Wales or Scotland?
No. These figures are the UK government's for England only. Wales and Scotland run their own building safety programmes.
Checked against GOV.UK on 10 November 2026.
No external wall firms are listed in the directory yet.
Does your firm carry out external wall assessments or remediation? List it free in the directory
Planning remediation on a building of 18 metres or more? See how long Gateway 2 approval for external wall remediation takes now
- The figures are the government's management information, not official statistics. They count residential buildings of 11 metres and over in England that the government monitors through its remediation programmes, the developer remediation contract and landlords' own reports.
- "Finished" includes buildings whose work is complete but awaiting building control sign-off. "Not started" means in a programme with work yet to begin.
- Councils are given as bands of buildings (11 to 50, 51 to 100, and so on), and those with fewer than 10 monitored buildings are left out, so that no single building can be identified. This page shows the bands as published and never combines them with other figures.
- Each table has its own date. Developer figures are quarterly, and council enforcement is counted to a slightly different day.
- From December 2025 social housing is counted from landlords' own reports, so earlier months are not shown.
- This is INFIRISK's analysis of the government's published data. The Ministry of Housing, Communities and Local Government has not reviewed or endorsed it. Boundaries: Office for National Statistics, contains OS data, Crown copyright and database right. Contains public sector information licensed under the Open Government Licence v3.0.
Releases used
- Building Safety Remediation: monthly data release, October 2026
- Building Safety Remediation: monthly data release, September 2026
- Building Safety Remediation: monthly data release, August 2026
- Building Safety Remediation: monthly data release, July 2026
- Building Safety Remediation: monthly data release, June 2026
- Building Safety Remediation: monthly data release, May 2026
- Building Safety Remediation: monthly data release, April 2026
- Building Safety Remediation: monthly data release, March 2026
- Building Safety Remediation: monthly data release, February 2026
- Building Safety Remediation: monthly data release, January 2026
- Building Safety Remediation: monthly data release, December 2025
Every release, and the government's own dashboard, on GOV.UK