Cladding remediation in Portsmouth

In Portsmouth (11 to 50 buildings monitored), work was finished on 40%, underway on 0% and not started on 60%, at 31 October 2026.

October 2026 release, figures at 31 October 2026

Finished

40%

of monitored buildings

Underway

0%

of monitored buildings

Not started

60%

of monitored buildings

Buildings monitored

11-50

A band, as published, at 31 October 2026

The share of monitored buildings at each stage, one point per monthly release. A gap is a month the council was not listed.

Show the figures as a table
Portsmouth: share of buildings at each stage by month
MonthBuildings monitoredFinishedUnderwayNot started
December 202511-5024%50%26%
January 202611-5024%50%26%
February 202611-5022%47%31%
March 202611-5022%47%31%
April 202611-5021%45%34%
May 202611-5021%17%62%
June 202611-5024%18%57%
July 202611-5025%17%58%
August 202611-5042%0%58%
September 202611-5041%0%59%
October 202611-5040%0%60%
Portsmouth within South East