Cladding remediation map

Cladding remediation in Hillingdon

In Hillingdon (11 to 50 buildings monitored), work was finished on 23%, underway on 26% and not started on 52%, at 31 October 2026.

October 2026 release, figures at 31 October 2026

Finished

23%

of monitored buildings

Underway

26%

of monitored buildings

Not started

52%

of monitored buildings

Buildings monitored

11-50

A band, as published, at 31 October 2026

The share of monitored buildings at each stage, one point per monthly release. A gap is a month the council was not listed.

Show the figures as a table
Hillingdon: share of buildings at each stage by month
MonthBuildings monitoredFinishedUnderwayNot started
December 202511-509%24%68%
January 202611-5011%20%69%
February 202611-5013%23%63%
March 202611-5013%23%63%
April 202611-5013%23%65%
May 202611-5016%23%61%
June 202611-5016%26%58%
July 202611-5016%32%52%
August 202611-5016%32%52%
September 202611-5016%32%52%
October 202611-5023%26%52%
Hillingdon within London