Cladding remediation map

Cladding remediation in Sunderland

In Sunderland (11 to 50 buildings monitored), work was finished on 64%, underway on 9% and not started on 27%, at 31 October 2026.

October 2026 release, figures at 31 October 2026

Finished

64%

of monitored buildings

Underway

9%

of monitored buildings

Not started

27%

of monitored buildings

Buildings monitored

11-50

A band, as published, at 31 October 2026

The share of monitored buildings at each stage, one point per monthly release. A gap is a month the council was not listed.

Show the figures as a table
Sunderland: share of buildings at each stage by month
MonthBuildings monitoredFinishedUnderwayNot started
December 202511-5054%8%38%
January 202611-5054%8%38%
February 202611-5054%8%38%
March 202611-5050%7%43%
April 202611-5050%7%43%
May 202611-5050%7%43%
June 202611-5050%7%43%
July 202611-5054%8%38%
August 202611-5064%9%27%
September 202611-5064%9%27%
October 202611-5064%9%27%
Sunderland within North East