Cladding remediation map

Cladding remediation in Brent

In Brent (51 to 100 buildings monitored), work was finished on 38%, underway on 16% and not started on 46%, at 31 October 2026.

October 2026 release, figures at 31 October 2026

Finished

38%

of monitored buildings

Underway

16%

of monitored buildings

Not started

46%

of monitored buildings

Buildings monitored

51-100

A band, as published, at 31 October 2026

The share of monitored buildings at each stage, one point per monthly release. A gap is a month the council was not listed.

Show the figures as a table
Brent: share of buildings at each stage by month
MonthBuildings monitoredFinishedUnderwayNot started
December 202551-10042%13%46%
January 202651-10040%12%49%
February 202651-10039%13%49%
March 202651-10039%14%47%
April 202651-10039%14%47%
May 202651-10041%13%47%
June 202651-10041%11%48%
July 202651-10041%11%48%
August 202651-10039%11%50%
September 202651-10039%12%49%
October 202651-10038%16%46%
Brent within London