Cladding remediation map

Cladding remediation in Slough

In Slough (11 to 50 buildings monitored), work was finished on 50%, underway on 5% and not started on 45%, at 31 October 2026.

October 2026 release, figures at 31 October 2026

Finished

50%

of monitored buildings

Underway

5%

of monitored buildings

Not started

45%

of monitored buildings

Buildings monitored

11-50

A band, as published, at 31 October 2026

The share of monitored buildings at each stage, one point per monthly release. A gap is a month the council was not listed.

Show the figures as a table
Slough: share of buildings at each stage by month
MonthBuildings monitoredFinishedUnderwayNot started
December 202511-5036%8%56%
January 202611-5036%8%56%
February 202611-5036%8%56%
March 202611-5036%8%56%
April 202611-5036%8%56%
May 202611-5043%10%48%
June 202611-5043%10%48%
July 202611-5043%10%48%
August 202611-5050%5%45%
September 202611-5050%5%45%
October 202611-5050%5%45%