Cladding remediation map

Cladding remediation in Plymouth

In Plymouth (11 to 50 buildings monitored), work was finished on 30%, underway on 23% and not started on 47%, at 31 October 2026.

October 2026 release, figures at 31 October 2026

Finished

30%

of monitored buildings

Underway

23%

of monitored buildings

Not started

47%

of monitored buildings

Buildings monitored

11-50

A band, as published, at 31 October 2026

The share of monitored buildings at each stage, one point per monthly release. A gap is a month the council was not listed.

Show the figures as a table
Plymouth: share of buildings at each stage by month
MonthBuildings monitoredFinishedUnderwayNot started
December 202511-5029%11%61%
January 202611-5027%10%63%
February 202611-5026%10%65%
March 202611-5026%16%58%
April 202611-5026%16%58%
May 202611-5029%13%58%
June 202611-5030%13%57%
July 202611-5030%17%53%
August 202611-5030%17%53%
September 202611-5030%23%47%
October 202611-5030%23%47%
Plymouth within South West