Cladding remediation map

Cladding remediation in Newham

In Newham (101 to 200 buildings monitored), work was finished on 42%, underway on 15% and not started on 43%, at 31 October 2026.

October 2026 release, figures at 31 October 2026

Finished

42%

of monitored buildings

Underway

15%

of monitored buildings

Not started

43%

of monitored buildings

Buildings monitored

101-200

A band, as published, at 31 October 2026

The share of monitored buildings at each stage, one point per monthly release. A gap is a month the council was not listed.

Show the figures as a table
Newham: share of buildings at each stage by month
MonthBuildings monitoredFinishedUnderwayNot started
December 2025101-20042%13%45%
January 2026101-20043%11%46%
February 2026101-20041%13%46%
March 2026101-20041%13%46%
April 2026101-20042%18%40%
May 2026101-20042%17%41%
June 2026101-20042%17%41%
July 2026101-20042%16%42%
August 2026101-20041%15%45%
September 2026101-20042%15%43%
October 2026101-20042%15%43%
Newham within London