Cladding remediation in Havering

In Havering (11 to 50 buildings monitored), work was finished on 44%, underway on 8% and not started on 47%, at 31 October 2026.

October 2026 release, figures at 31 October 2026

Finished

44%

of monitored buildings

Underway

8%

of monitored buildings

Not started

47%

of monitored buildings

Buildings monitored

11-50

A band, as published, at 31 October 2026

The share of monitored buildings at each stage, one point per monthly release. A gap is a month the council was not listed.

Show the figures as a table
Havering: share of buildings at each stage by month
MonthBuildings monitoredFinishedUnderwayNot started
December 202511-5057%7%37%
January 202611-5057%7%37%
February 202611-5057%7%37%
March 202611-5057%7%37%
April 202611-5058%3%39%
May 202611-5052%6%42%
June 202611-5052%6%42%
July 202611-5049%5%46%
August 202611-5043%8%49%
September 202611-5043%8%49%
October 202611-5044%8%47%