Cladding remediation map

Cladding remediation in Newcastle upon Tyne

In Newcastle upon Tyne (11 to 50 buildings monitored), work was finished on 50%, underway on 9% and not started on 41%, at 31 October 2026.

October 2026 release, figures at 31 October 2026

Finished

50%

of monitored buildings

Underway

9%

of monitored buildings

Not started

41%

of monitored buildings

Buildings monitored

11-50

A band, as published, at 31 October 2026

The share of monitored buildings at each stage, one point per monthly release. A gap is a month the council was not listed.

Show the figures as a table
Newcastle upon Tyne: share of buildings at each stage by month
MonthBuildings monitoredFinishedUnderwayNot started
December 202511-5045%24%31%
January 202611-5045%24%31%
February 202611-5055%14%31%
March 202611-5055%17%28%
April 202611-5055%17%28%
May 202611-5053%10%37%
June 202611-5052%10%39%
July 202611-5050%9%41%
August 202611-5050%9%41%
September 202611-5050%9%41%
October 202611-5050%9%41%
Newcastle upon Tyne within North East