Cladding remediation map

Cladding remediation in Sutton

In Sutton (11 to 50 buildings monitored), work was finished on 42%, underway on 5% and not started on 53%, at 31 October 2026.

October 2026 release, figures at 31 October 2026

Finished

42%

of monitored buildings

Underway

5%

of monitored buildings

Not started

53%

of monitored buildings

Buildings monitored

11-50

A band, as published, at 31 October 2026

The share of monitored buildings at each stage, one point per monthly release. A gap is a month the council was not listed.

Show the figures as a table
Sutton: share of buildings at each stage by month
MonthBuildings monitoredFinishedUnderwayNot started
December 202511-5029%19%52%
January 202611-5029%19%52%
February 202611-5029%19%52%
March 202611-5029%19%52%
April 202611-5038%19%43%
May 202611-5040%5%55%
June 202611-5040%5%55%
July 202611-5042%5%53%
August 202611-5045%5%50%
September 202611-5045%5%50%
October 202611-5042%5%53%