Cladding remediation in Hammersmith and Fulham

In Hammersmith and Fulham (11 to 50 buildings monitored), work was finished on 27%, underway on 11% and not started on 62%, at 31 October 2026.

October 2026 release, figures at 31 October 2026

Finished

27%

of monitored buildings

Underway

11%

of monitored buildings

Not started

62%

of monitored buildings

Buildings monitored

11-50

A band, as published, at 31 October 2026

The share of monitored buildings at each stage, one point per monthly release. A gap is a month the council was not listed.

Show the figures as a table
Hammersmith and Fulham: share of buildings at each stage by month
MonthBuildings monitoredFinishedUnderwayNot started
December 202511-5026%2%72%
January 202611-5026%2%72%
February 202611-5027%0%73%
March 202611-5027%7%67%
April 202611-5028%7%65%
May 202611-5028%7%65%
June 202611-5028%11%61%
July 202611-5027%11%62%
August 202611-5027%11%62%
September 202611-5027%11%62%
October 202611-5027%11%62%