Gateway 2 tracker
How the Building Safety Regulator is handling building control approval for higher-risk buildings in England, updated each month from its own data.
In the 12 weeks to 1 November 2026 the Building Safety Regulator approved 95% of applications for new high-rise buildings, taking a median of 20 weeks.
Higher-risk buildings start at 18 metres or seven storeys. See in 3D what a block of flats needs from 18 m
August to October 2026 edition, figures to 1 November 2026, published 6 November 2026
New high-rise buildings
95%
approved
20 weeks
median to approval
Down 1 point3 weeks quicker
External wall remediation
93%
approved
32 weeks
median to approval
Up 6 points
Internal works
91%
approved
30 weeks
median to approval
Up 6 points1 week quicker
NHS internal works
86%
approved
20 weeks
median to approval
Up 5 points
One point per edition, labelled by the last day it covers. Each covers a rolling 12 weeks, so neighbouring points share most of their weeks.
External wall remediation on higher-risk buildings (18 metres or seven storeys and over) needs Gateway 2 approval. See how remediation itself is progressing, council by council
Approval rate
Show the figures as a table
| 12 weeks to | New high-rise buildings | External wall remediation | Internal works | NHS internal works |
|---|---|---|---|---|
| 29 March 2026 | 61% | 61% | n/a | n/a |
| 3 May 2026 | 73% | 72% | n/a | n/a |
| 31 May 2026 | 90% | 79% | n/a | n/a |
| 28 June 2026 | 89% | 85% | 73% | n/a |
| 2 August 2026 | 91% | 85% | 77% | 84% |
| 30 August 2026 | 92% | 89% | 78% | 82% |
| 4 October 2026 | 96% | 87% | 85% | 81% |
| 1 November 2026 | 95% | 93% | 91% | 86% |
Median weeks to approval
Show the figures as a table
| 12 weeks to | New high-rise buildings | External wall remediation | Internal works | NHS internal works |
|---|---|---|---|---|
| 29 March 2026 | 22 | 36 | n/a | n/a |
| 3 May 2026 | 22 | 46 | n/a | n/a |
| 31 May 2026 | 22 | 39 | n/a | n/a |
| 28 June 2026 | 22 | 35 | 28 | n/a |
| 2 August 2026 | 22 | 34 | 32 | 24 |
| 30 August 2026 | 22 | 33 | 32 | 22 |
| 4 October 2026 | 23 | 32 | 31 | 20 |
| 1 November 2026 | 20 | 32 | 30 | 20 |
Every type of work, week by week since April 2026. Where editions overlap, the newest figure for each week is used, because the regulator revises recent weeks.
Show the figures as a table
| Week commencing | Applications in | Decisions out | Waiting |
|---|---|---|---|
| 6 April 2026 | 47 | 40 | 1,536 |
| 13 April 2026 | 50 | 37 | 1,549 |
| 20 April 2026 | 62 | 62 | 1,549 |
| 27 April 2026 | 66 | 69 | 1,546 |
| 4 May 2026 | 78 | 51 | 1,573 |
| 11 May 2026 | 72 | 122 | 1,521 |
| 18 May 2026 | 57 | 88 | 1,490 |
| 25 May 2026 | 42 | 53 | 1,479 |
| 1 June 2026 | 81 | 58 | 1,502 |
| 8 June 2026 | 55 | 49 | 1,515 |
| 15 June 2026 | 55 | 49 | 1,521 |
| 22 June 2026 | 53 | 48 | 1,526 |
| 29 June 2026 | 55 | 37 | 1,544 |
| 6 July 2026 | 51 | 39 | 1,556 |
| 13 July 2026 | 46 | 60 | 1,542 |
| 20 July 2026 | 47 | 39 | 1,550 |
| 27 July 2026 | 56 | 53 | 1,553 |
| 3 August 2026 | 62 | 34 | 1,581 |
| 10 August 2026 | 48 | 25 | 1,603 |
| 17 August 2026 | 71 | 50 | 1,624 |
| 24 August 2026 | 100 | 60 | 1,664 |
| 31 August 2026 | 41 | 34 | 1,671 |
| 7 September 2026 | 50 | 46 | 1,675 |
| 14 September 2026 | 46 | 38 | 1,683 |
| 21 September 2026 | 79 | 68 | 1,694 |
| 28 September 2026 | 76 | 62 | 1,708 |
| 5 October 2026 | 40 | 65 | 1,683 |
| 12 October 2026 | 44 | 43 | 1,684 |
| 19 October 2026 | 57 | 56 | 1,685 |
| 26 October 2026 | 45 | 43 | 1,687 |
Cases in progress with a recorded region, at the end of the latest 12 weeks. They add up to less than the national total, so read them as a share, not a count of every case.
Show the figures as a table
| Region | New high-rise buildings | External wall remediation | Internal works | NHS internal works | Total |
|---|---|---|---|---|---|
| London | 110 | 171 | 751 | 18 | 1,050 |
| South West | 6 | 24 | 78 | 3 | 111 |
| North West | 17 | 30 | 48 | 2 | 97 |
| South East | 8 | 23 | 44 | 3 | 78 |
| East of England | 4 | 11 | 44 | 1 | 60 |
| West Midlands | 10 | 2 | 37 | 0 | 49 |
| North East | 0 | 10 | 34 | 2 | 46 |
| Yorkshire and the Humber | 3 | 8 | 32 | 2 | 45 |
| East Midlands | 0 | 10 | 26 | 2 | 38 |
Gateway 3: before people move in
No new high-rise building has reached Gateway 3 yet; the applications so far are for work to existing buildings.
Show Gateway 3 applications in progress by week
| Week commencing | In progress |
|---|---|
| 6 April 2026 | 132 |
| 13 April 2026 | 129 |
| 20 April 2026 | 124 |
| 27 April 2026 | 121 |
| 4 May 2026 | 122 |
| 11 May 2026 | 123 |
| 18 May 2026 | 122 |
| 25 May 2026 | 128 |
| 1 June 2026 | 128 |
| 8 June 2026 | 126 |
| 15 June 2026 | 131 |
| 22 June 2026 | 134 |
| 29 June 2026 | 128 |
| 6 July 2026 | 133 |
| 13 July 2026 | 131 |
| 20 July 2026 | 132 |
| 27 July 2026 | 135 |
| 3 August 2026 | 142 |
| 10 August 2026 | 135 |
| 17 August 2026 | 138 |
| 24 August 2026 | 144 |
| 31 August 2026 | 146 |
| 7 September 2026 | 146 |
| 14 September 2026 | 140 |
| 21 September 2026 | 144 |
| 28 September 2026 | 150 |
| 5 October 2026 | 156 |
| 12 October 2026 | 157 |
| 19 October 2026 | 158 |
| 26 October 2026 | 155 |
Show Gateway 3 by type of work
| Type of work | In progress | New in | Approved | Homes |
|---|---|---|---|---|
| New high-rise buildings | 0 | 0 | 0 | 0 |
| External wall remediation | 7 | 4 | 3 | 549 |
| Internal works | 109 | 54 | 24 | n/a |
| NHS internal works | 13 | 4 | 1 | n/a |
Major changes during building work
Once work has started, significant changes to the approved design need the regulator's approval too.
Show major change requests by type of work
| Type of work | In progress | New in | Closed | Median weeks to close |
|---|---|---|---|---|
| New high-rise buildings | 109 | 109 | 80 | 7 |
| External wall remediation | 32 | 27 | 20 | 16 |
| Internal works | 75 | 42 | 29 | 26 |
| NHS internal works | 23 | 10 | 8 | 16 |
People working on applications
175 regulator staff, 514 external specialists, 62 specialists working inside its teams, at the end of the latest 12 weeks.
Show people working on applications by week
| Week commencing | People |
|---|---|
| 6 April 2026 | 296 |
| 13 April 2026 | 332 |
| 20 April 2026 | 344 |
| 27 April 2026 | 345 |
| 4 May 2026 | 330 |
| 11 May 2026 | 343 |
| 18 May 2026 | 358 |
| 25 May 2026 | 326 |
| 1 June 2026 | 380 |
| 8 June 2026 | 391 |
| 15 June 2026 | 377 |
| 22 June 2026 | 378 |
| 29 June 2026 | 387 |
| 6 July 2026 | 397 |
| 13 July 2026 | 411 |
| 20 July 2026 | 409 |
| 27 July 2026 | 383 |
| 3 August 2026 | 374 |
| 10 August 2026 | 387 |
| 17 August 2026 | 380 |
| 24 August 2026 | 388 |
| 31 August 2026 | 384 |
| 7 September 2026 | 421 |
| 14 September 2026 | 429 |
| 21 September 2026 | 437 |
| 28 September 2026 | 426 |
| 5 October 2026 | 418 |
| 12 October 2026 | 401 |
| 19 October 2026 | 456 |
| 26 October 2026 | 374 |
If you are planning high-rise work
Plan for the median, not the 12 weeks in the guidance: 20 weeks for a new building in the latest figures, 30 for internal works and 32 for external wall remediation. Approval rates differ by type of work: 95% for new buildings against 91% for internal works. The regulator's guidance sets out what a complete application contains; an incomplete one risks a rejection and a second wait.
If you live in a tall building
Gateway 2 is where the regulator checks the design of a tall building, or of work to one, before building starts. The approval rate counts approvals against approvals plus rejections, so it leaves out applications found invalid or withdrawn (4 for new buildings in the latest 12 weeks). A high rate means most applications that reach a decision are approved, not that every application is.
If your firm prepares or reviews submissions
At the end of the latest 12 weeks, 1,116 internal works applications were waiting for a decision, against 183 for new buildings and 292 for external wall remediation. London holds 67% of the cases with a recorded region.
- Gateway 1, at planning. Since 1 August 2021, a planning application for a building of 18 metres or seven storeys or more with two or more homes has needed a fire statement, and the regulator is consulted on fire safety.
- Gateway 2, before building work starts. The regulator, as the building control authority for higher-risk buildings, must approve the design. Work cannot start until it does. This page tracks Gateway 2.
- Gateway 3, before people move in. The regulator must issue a completion certificate, and the building must be registered, before it can be occupied.
What is Gateway 2?
Gateway 2 is the point before building work starts on a higher-risk building in England (at least 18 metres or seven storeys tall, with at least two homes, or a care home or hospital of that height). Work cannot start until the Building Safety Regulator, acting as the building control authority, has approved the application.
How long does Gateway 2 take?
In the 12 weeks to 1 November 2026, the median time to approve an application for a new high-rise building was 20 weeks, and 32 weeks for external wall remediation. The regulator's guidance says it will take up to 12 weeks for a new higher-risk building and 8 weeks for work to an existing one, unless an extension is agreed, and that the time depends on the quality of the application.
How often are Gateway 2 applications rejected?
In the 12 weeks to 1 November 2026, 95% of decided applications for new high-rise buildings were approved and 5% rejected. The rate counts approvals against approvals plus rejections; applications found invalid or withdrawn are left out.
Why are Gateway 2 applications rejected?
The regulator's own commentary points to applications that are incomplete or show significant gaps in compliance. In its October 2026 release it said every decision to reject now goes through two further levels of review, and that it rejects only where there is no realistic prospect of approval in a reasonable time. Its guidance on building control approval for higher-risk buildings sets out what a complete application contains.
Does Gateway 2 apply in Wales or Scotland?
No. The Building Safety Regulator is the building control authority for higher-risk buildings in England only. Wales and Scotland have their own building regulations and approval regimes, so these figures cover England.
The regulator's guidance on building control approval for higher-risk buildings
- New buildings and internal works: No fire strategy firms are listed for this yet.
- External wall remediation: No external wall firms are listed for this yet.
Does your firm prepare Gateway 2 submissions? List it free in the directory
- The approval rate is approvals divided by approvals plus rejections. Applications found invalid or withdrawn are left out.
- Each figure covers a rolling 12 weeks, or counts the cases in progress at the end of them. Editions overlap, and later editions revise recent weeks.
- Where the regulator's headline table and its detail table differ by a point, this page uses the detail table every month.
- Before April 2026 the regulator reported new builds for its Innovation Unit, which left out a few older cases; those figures are shown as new builds. Internal works start in April 2026 and NHS works in May 2026.
- The regional figures count cases in progress with a recorded region, so they add up to less than the national total.
- These are transparency data, not official statistics, and they cover England only. Editions before January to March 2026 used different categories and counted percentages against all closed cases, so they are not shown.
- This is INFIRISK's analysis of the regulator's published data. The regulator has not reviewed or endorsed it. Contains public sector information licensed under the Open Government Licence v3.0.
Editions used
- Building control approval application data, August to October 2026
- Building control approval application data, July to September 2026
- Building control approval application data, June to August 2026
- Building control approval application data, May to July 2026
- Building control approval application data, April to June 2026
- Building control approval application data, March to May 2026
- Building control approval application data, February to April 2026
- Building control approval application data, January to March 2026