Cladding remediation in Bromley

In Bromley (11 to 50 buildings monitored), work was finished on 39%, underway on 6% and not started on 56%, at 31 October 2026.

October 2026 release, figures at 31 October 2026

Finished

39%

of monitored buildings

Underway

6%

of monitored buildings

Not started

56%

of monitored buildings

Buildings monitored

11-50

A band, as published, at 31 October 2026

The share of monitored buildings at each stage, one point per monthly release. A gap is a month the council was not listed.

Show the figures as a table
Bromley: share of buildings at each stage by month
MonthBuildings monitoredFinishedUnderwayNot started
December 202511-5025%6%69%
January 202611-5025%6%69%
February 202611-5028%11%61%
March 202611-5028%11%61%
April 202611-5024%12%65%
May 202611-5035%5%60%
June 202611-5035%5%60%
July 202611-5035%5%60%
August 202611-5039%6%56%
September 202611-5039%6%56%
October 202611-5039%6%56%