Cladding remediation map

Cladding remediation in Reading

In Reading (11 to 50 buildings monitored), work was finished on 53%, underway on 17% and not started on 30%, at 31 October 2026.

October 2026 release, figures at 31 October 2026

Finished

53%

of monitored buildings

Underway

17%

of monitored buildings

Not started

30%

of monitored buildings

Buildings monitored

11-50

A band, as published, at 31 October 2026

The share of monitored buildings at each stage, one point per monthly release. A gap is a month the council was not listed.

Show the figures as a table
Reading: share of buildings at each stage by month
MonthBuildings monitoredFinishedUnderwayNot started
December 202511-5054%14%32%
January 202611-5054%14%32%
February 202611-5058%8%35%
March 202611-5058%8%35%
April 202611-5052%7%41%
May 202611-5053%10%37%
June 202611-5053%10%37%
July 202611-5053%10%37%
August 202611-5053%17%30%
September 202611-5053%17%30%
October 202611-5053%17%30%
Reading within South East