In Leeds (51 to 100 buildings monitored), work was finished on 54%, underway on 24% and not started on 22%, at 31 October 2026.
October 2026 release, figures at 31 October 2026
Finished
54%
of monitored buildings
Underway
24%
of monitored buildings
Not started
22%
of monitored buildings
Buildings monitored
51-100
A band, as published, at 31 October 2026
The share of monitored buildings at each stage, one point per monthly release. A gap is a month the council was not listed.
Show the figures as a table
| Month | Buildings monitored | Finished | Underway | Not started |
|---|---|---|---|---|
| December 2025 | 51-100 | 41% | 24% | 35% |
| January 2026 | 51-100 | 42% | 23% | 35% |
| February 2026 | 51-100 | 43% | 23% | 34% |
| March 2026 | 51-100 | 43% | 24% | 32% |
| April 2026 | 51-100 | 43% | 22% | 35% |
| May 2026 | 51-100 | 47% | 17% | 36% |
| June 2026 | 51-100 | 47% | 17% | 36% |
| July 2026 | 51-100 | 52% | 12% | 36% |
| August 2026 | 51-100 | 53% | 14% | 32% |
| September 2026 | 51-100 | 53% | 15% | 32% |
| October 2026 | 51-100 | 54% | 24% | 22% |
| Buildings monitored | Finished | Underway | Not started | |
|---|---|---|---|---|
| Leeds | 51 to 100 buildings | 54% | 24% | 22% |
| Yorkshire and The Humber | 161 | 49% | 20% | 30% |
| England | 4,740 | 40% | 16% | 44% |
What Leeds has done under the Housing Act 2004 against buildings with unsafe cladding, at 31 October 2026.
- Buildings acted on
- 0
- Rated category 1
- 0
- Rated category 2
- 0
- Notices served
- 0
- Improvement notices
- 0
- Hazard awareness notices
- 0
- Prohibition orders
- 0
- Inspected with the inspection team
- 0
Other councils in Yorkshire and The Humber
- Fire statistics for West Yorkshire Fire and Rescue Service
- No external wall firms are listed in the directory yet. List yours free
- Every council on the map, with method and sources