Cladding remediation map

Cladding remediation in Gosport

In Gosport (11 to 50 buildings monitored), work was finished on 73%, underway on 0% and not started on 27%, at 31 October 2026.

October 2026 release, figures at 31 October 2026

Finished

73%

of monitored buildings

Underway

0%

of monitored buildings

Not started

27%

of monitored buildings

Buildings monitored

11-50

A band, as published, at 31 October 2026

The share of monitored buildings at each stage, one point per monthly release. A gap is a month the council was not listed.

Show the figures as a table
Gosport: share of buildings at each stage by month
MonthBuildings monitoredFinishedUnderwayNot started
December 2025Not listedn/an/an/a
January 2026Not listedn/an/an/a
February 2026Not listedn/an/an/a
March 2026Not listedn/an/an/a
April 2026Not listedn/an/an/a
May 2026Not listedn/an/an/a
June 2026Not listedn/an/an/a
July 202611-5064%9%27%
August 202611-5073%0%27%
September 202611-5073%0%27%
October 202611-5073%0%27%
Gosport within South East