Cladding remediation map

Cladding remediation in Cambridge

In Cambridge (11 to 50 buildings monitored), work was finished on 16%, underway on 10% and not started on 73%, at 31 October 2026.

October 2026 release, figures at 31 October 2026

Finished

16%

of monitored buildings

Underway

10%

of monitored buildings

Not started

73%

of monitored buildings

Buildings monitored

11-50

A band, as published, at 31 October 2026

The share of monitored buildings at each stage, one point per monthly release. A gap is a month the council was not listed.

Show the figures as a table
Cambridge: share of buildings at each stage by month
MonthBuildings monitoredFinishedUnderwayNot started
December 202511-5011%17%72%
January 202611-5011%17%72%
February 202611-5015%27%58%
March 202611-5015%27%58%
April 202611-5014%27%59%
May 202611-5014%8%78%
June 202611-5014%8%78%
July 202611-5014%8%78%
August 202611-5014%10%76%
September 202611-5014%12%73%
October 202611-5016%10%73%
Cambridge within East of England