Cladding remediation in Liverpool

In Liverpool (51 to 100 buildings monitored), work was finished on 35%, underway on 22% and not started on 43%, at 31 October 2026.

October 2026 release, figures at 31 October 2026

Finished

35%

of monitored buildings

Underway

22%

of monitored buildings

Not started

43%

of monitored buildings

Buildings monitored

51-100

A band, as published, at 31 October 2026

The share of monitored buildings at each stage, one point per monthly release. A gap is a month the council was not listed.

Show the figures as a table
Liverpool: share of buildings at each stage by month
MonthBuildings monitoredFinishedUnderwayNot started
December 202551-10031%16%53%
January 202651-10030%16%53%
February 202651-10029%17%54%
March 202651-10029%20%51%
April 2026101-20028%20%52%
May 202651-10028%20%52%
June 2026101-20029%20%51%
July 2026101-20029%19%51%
August 2026101-20030%18%52%
September 2026101-20031%21%48%
October 202651-10035%22%43%
Liverpool within North West