Cladding remediation in Southampton

In Southampton (101 to 200 buildings monitored), work was finished on 49%, underway on 13% and not started on 38%, at 31 October 2026.

October 2026 release, figures at 31 October 2026

Finished

49%

of monitored buildings

Underway

13%

of monitored buildings

Not started

38%

of monitored buildings

Buildings monitored

101-200

A band, as published, at 31 October 2026

The share of monitored buildings at each stage, one point per monthly release. A gap is a month the council was not listed.

Show the figures as a table
Southampton: share of buildings at each stage by month
MonthBuildings monitoredFinishedUnderwayNot started
December 2025101-20068%12%20%
January 2026101-20068%12%20%
February 2026101-20068%11%20%
March 2026101-20068%12%20%
April 2026101-20069%12%20%
May 2026101-20078%2%20%
June 2026101-20077%3%21%
July 2026101-20050%25%25%
August 2026101-20049%13%38%
September 2026101-20050%13%38%
October 2026101-20049%13%38%
Southampton within South East