Cladding remediation map

Cladding remediation in Bexley

In Bexley (11 to 50 buildings monitored), work was finished on 47%, underway on 26% and not started on 26%, at 31 October 2026.

October 2026 release, figures at 31 October 2026

Finished

47%

of monitored buildings

Underway

26%

of monitored buildings

Not started

26%

of monitored buildings

Buildings monitored

11-50

A band, as published, at 31 October 2026

The share of monitored buildings at each stage, one point per monthly release. A gap is a month the council was not listed.

Show the figures as a table
Bexley: share of buildings at each stage by month
MonthBuildings monitoredFinishedUnderwayNot started
December 202511-5054%0%46%
January 202611-5054%0%46%
February 202611-5052%0%48%
March 202611-5052%0%48%
April 202611-5052%0%48%
May 202611-5064%0%36%
June 202611-5064%0%36%
July 202611-5061%0%39%
August 202611-5061%22%17%
September 202611-5052%24%24%
October 202611-5047%26%26%
Bexley within London