Cladding remediation in Basingstoke and Deane

In Basingstoke and Deane (11 to 50 buildings monitored), work was finished on 29%, underway on 52% and not started on 19%, at 31 October 2026.

October 2026 release, figures at 31 October 2026

Finished

29%

of monitored buildings

Underway

52%

of monitored buildings

Not started

19%

of monitored buildings

Buildings monitored

11-50

A band, as published, at 31 October 2026

The share of monitored buildings at each stage, one point per monthly release. A gap is a month the council was not listed.

Show the figures as a table
Basingstoke and Deane: share of buildings at each stage by month
MonthBuildings monitoredFinishedUnderwayNot started
December 202511-5038%31%31%
January 202611-5035%29%35%
February 202611-5017%44%39%
March 202611-5017%44%39%
April 202611-5017%44%39%
May 202611-5032%42%26%
June 202611-5029%38%33%
July 202611-5029%38%33%
August 202611-5029%38%33%
September 202611-5029%43%29%
October 202611-5029%52%19%
Basingstoke and Deane within South East