Cladding remediation map

Cladding remediation in Leicester

In Leicester (11 to 50 buildings monitored), work was finished on 28%, underway on 20% and not started on 52%, at 31 October 2026.

October 2026 release, figures at 31 October 2026

Finished

28%

of monitored buildings

Underway

20%

of monitored buildings

Not started

52%

of monitored buildings

Buildings monitored

11-50

A band, as published, at 31 October 2026

The share of monitored buildings at each stage, one point per monthly release. A gap is a month the council was not listed.

Show the figures as a table
Leicester: share of buildings at each stage by month
MonthBuildings monitoredFinishedUnderwayNot started
December 202511-5021%4%75%
January 202611-5017%8%75%
February 202611-5017%8%75%
March 202611-5021%13%67%
April 202611-5021%17%63%
May 202611-5021%17%63%
June 202611-5021%17%63%
July 202611-5028%20%52%
August 202611-5028%20%52%
September 202611-5028%20%52%
October 202611-5028%20%52%
Leicester within East Midlands