Cladding remediation map

Cladding remediation in Bournemouth, Christchurch and Poole

In Bournemouth, Christchurch and Poole (11 to 50 buildings monitored), work was finished on 46%, underway on 7% and not started on 48%, at 31 October 2026.

October 2026 release, figures at 31 October 2026

Finished

46%

of monitored buildings

Underway

7%

of monitored buildings

Not started

48%

of monitored buildings

Buildings monitored

11-50

A band, as published, at 31 October 2026

The share of monitored buildings at each stage, one point per monthly release. A gap is a month the council was not listed.

Show the figures as a table
Bournemouth, Christchurch and Poole: share of buildings at each stage by month
MonthBuildings monitoredFinishedUnderwayNot started
December 202511-5031%40%29%
January 202611-5033%38%29%
February 202611-5034%41%24%
March 202611-5034%41%24%
April 202611-5037%41%22%
May 202611-5044%7%49%
June 202611-5044%7%49%
July 202611-5043%7%50%
August 202611-5043%9%48%
September 202611-5042%9%49%
October 202611-5046%7%48%
Bournemouth, Christchurch and Poole within South West