Cladding remediation map

Cladding remediation in Kensington and Chelsea

In Kensington and Chelsea (11 to 50 buildings monitored), work was finished on 45%, underway on 27% and not started on 27%, at 31 October 2026.

October 2026 release, figures at 31 October 2026

Finished

45%

of monitored buildings

Underway

27%

of monitored buildings

Not started

27%

of monitored buildings

Buildings monitored

11-50

A band, as published, at 31 October 2026

The share of monitored buildings at each stage, one point per monthly release. A gap is a month the council was not listed.

Show the figures as a table
Kensington and Chelsea: share of buildings at each stage by month
MonthBuildings monitoredFinishedUnderwayNot started
December 202511-5022%56%22%
January 202611-5022%56%22%
February 202611-5017%43%39%
March 202611-5017%43%39%
April 202611-5018%41%41%
May 202611-5045%14%41%
June 202611-5045%18%36%
July 202611-5043%22%35%
August 202611-5043%22%35%
September 202611-5045%27%27%
October 202611-5045%27%27%