Cladding remediation map

Cladding remediation in Trafford

In Trafford (11 to 50 buildings monitored), work was finished on 37%, underway on 5% and not started on 58%, at 31 October 2026.

October 2026 release, figures at 31 October 2026

Finished

37%

of monitored buildings

Underway

5%

of monitored buildings

Not started

58%

of monitored buildings

Buildings monitored

11-50

A band, as published, at 31 October 2026

The share of monitored buildings at each stage, one point per monthly release. A gap is a month the council was not listed.

Show the figures as a table
Trafford: share of buildings at each stage by month
MonthBuildings monitoredFinishedUnderwayNot started
December 202511-5033%7%60%
January 202611-5033%7%60%
February 202611-5044%6%50%
March 202611-5044%6%50%
April 202611-5036%7%57%
May 202611-5033%7%60%
June 202611-5031%6%63%
July 202611-5037%5%58%
August 202611-5037%5%58%
September 202611-5037%5%58%
October 202611-5037%5%58%
Trafford within North West