Cladding remediation map

Cladding remediation in Manchester

In Manchester (201 to 400 buildings monitored), work was finished on 48%, underway on 13% and not started on 39%, at 31 October 2026.

October 2026 release, figures at 31 October 2026

Finished

48%

of monitored buildings

Underway

13%

of monitored buildings

Not started

39%

of monitored buildings

Buildings monitored

201-400

A band, as published, at 31 October 2026

The share of monitored buildings at each stage, one point per monthly release. A gap is a month the council was not listed.

Show the figures as a table
Manchester: share of buildings at each stage by month
MonthBuildings monitoredFinishedUnderwayNot started
December 2025101-20045%12%43%
January 2026101-20045%13%42%
February 2026101-20043%13%45%
March 2026101-20043%15%43%
April 2026201-40043%14%43%
May 2026201-40045%14%41%
June 2026201-40045%17%39%
July 2026201-40046%13%41%
August 2026201-40046%14%40%
September 2026201-40048%13%39%
October 2026201-40048%13%39%
Manchester within North West