Cladding remediation map

Cladding remediation in Medway

In Medway (11 to 50 buildings monitored), work was finished on 44%, underway on 11% and not started on 44%, at 31 October 2026.

October 2026 release, figures at 31 October 2026

Finished

44%

of monitored buildings

Underway

11%

of monitored buildings

Not started

44%

of monitored buildings

Buildings monitored

11-50

A band, as published, at 31 October 2026

The share of monitored buildings at each stage, one point per monthly release. A gap is a month the council was not listed.

Show the figures as a table
Medway: share of buildings at each stage by month
MonthBuildings monitoredFinishedUnderwayNot started
December 202511-5067%0%33%
January 202611-5067%8%25%
February 202611-5053%6%41%
March 202611-5053%6%41%
April 202611-5050%6%44%
May 202611-5044%6%50%
June 202611-5044%6%50%
July 202611-5042%5%53%
August 202611-5042%11%47%
September 202611-5044%11%44%
October 202611-5044%11%44%
Medway within South East