Cladding remediation map

Cladding remediation in Lewisham

In Lewisham (51 to 100 buildings monitored), work was finished on 34%, underway on 16% and not started on 51%, at 31 October 2026.

October 2026 release, figures at 31 October 2026

Finished

34%

of monitored buildings

Underway

16%

of monitored buildings

Not started

51%

of monitored buildings

Buildings monitored

51-100

A band, as published, at 31 October 2026

The share of monitored buildings at each stage, one point per monthly release. A gap is a month the council was not listed.

Show the figures as a table
Lewisham: share of buildings at each stage by month
MonthBuildings monitoredFinishedUnderwayNot started
December 202551-10043%10%47%
January 202651-10042%17%41%
February 202651-10040%16%44%
March 202651-10041%17%42%
April 202651-10039%17%44%
May 202651-10039%14%48%
June 202651-10040%16%44%
July 202651-10035%14%51%
August 202651-10032%15%53%
September 202651-10034%16%50%
October 202651-10034%16%51%
Lewisham within London