Comprehensive Guidance on Building Control Approval for Higher-Risk Projects

New guidance on building control approval for higher-risk buildings is crucial for UK fire safety professionals.

INFIRISK Team4 min read
Comprehensive Guidance on Building Control Approval for Higher-Risk Projects
Photo by Павел Хлыстунов on Pexels

The UK government has released updated guidance on building control approval for higher-risk buildings, which is essential for professionals involved in the planning and modification of such structures. This guidance, published by the Building Safety Regulator (BSR), outlines the necessary steps and documentation required to ensure compliance with safety standards and regulatory requirements.

Understanding Higher-Risk Buildings

Higher-risk buildings are defined as those with at least seven storeys or a height of 18 metres, and include structures with two or more residential units, hospitals, or care homes. These buildings require registration with the BSR before occupancy. The guidance provides detailed instructions on the information needed for building control approval applications, which is crucial for ensuring these buildings meet safety standards.

Application Process and Requirements

The application process for building control approval involves submitting detailed information online, including the applicant's details, client authorisation, and contact information for the principal designer and contractor. Applicants must also provide comprehensive drawings and plans that demonstrate compliance with building regulations. The guidance emphasises the importance of keeping contact details up to date and managing applications through an assigned case officer.

The Building Safety Regulator oversees and approves building work for higher-risk buildings, which are defined as having at least seven storeys or being at least 18 metres high. These buildings must be registered with the BSR before they can be occupied. The guidance specifies the types of building work that require approval, as well as the information needed for the application, such as the building's name and location, proposed work description, and details about the building's height and number of storeys.

Changes to Approved Projects

Once a project is approved, any changes must be managed carefully. The guidance categorises changes as either notifiable or major, each requiring different levels of approval from the BSR. Notifiable changes include alterations that could affect compliance with building regulations, while major changes involve significant modifications that undermine the original approval basis. All changes must be recorded in a change control log, and major changes require BSR approval before work can proceed.

Notifiable changes must be communicated to the BSR before any related building work begins. These changes include modifications to the layout or dimensions within individual residential units that do not affect common areas, changes to openings for pipes or cables, and alterations to fire compliance statements. Major changes, such as those affecting the building's external dimensions or fire safety measures, require BSR approval before implementation.

Staged Applications for Complex Projects

For complex projects, the guidance allows for staged applications, where building work is divided into different phases. Each stage must be approved separately, and the BSR assesses these applications on a case-by-case basis. This approach is particularly useful for projects involving multiple towers or single towers with limited below-ground levels. The guidance outlines the documentation required for each stage, including a staged work statement and a partial completion strategy if applicable.

INFIRISK

Expert insights and guidance from the INFIRISK editorial team, covering fire safety regulations, industry standards, and best practices.

Staged applications are beneficial for managing large-scale projects with multiple phases. Each stage of the project must be clearly defined, and the BSR will review the application for each phase, ensuring compliance with building regulations at every step. This process helps streamline the approval and construction process, allowing for more efficient project management.

The Role of the Building Safety Regulator

The Building Safety Regulator plays a crucial role in overseeing the safety and compliance of higher-risk buildings. It is responsible for ensuring that all building work meets the necessary safety standards and that any changes to approved projects are properly managed. The BSR's involvement in the approval process helps maintain high safety standards and ensures that any potential risks are addressed promptly.

The BSR also manages the building safety levy, which applies to staged applications that create ten or more residential units. This levy is assessed separately for each stage, and the BSR cannot issue a partial completion certificate until the levy for each completed stage has been paid.

Practical Takeaways for UK Fire Safety Professionals

  • Ensure all higher-risk buildings are registered with the BSR before occupancy.

  • Submit comprehensive and accurate documentation for building control approval applications.

  • Manage and record all changes to approved projects in accordance with the guidance.

  • Consider staged applications for complex projects to streamline approval processes.

  • Stay informed about the building safety levy and ensure compliance with its requirements.

Sources

For more detailed information, refer to the guidance provided by the Building Safety Regulator on GOV.UK and making changes to a higher-risk building project.